试卷简介

2018年下半年全国计算机技术与软件专业技术资格(水平)考试信息系统项目管理师上午试卷及答案解析

1()is a tehnique for estimating the duration or cost of anactivity or a project using historical data from a similar activity or project.

A.Analogous estimating
B.parametric estimating
C.Three-Point estimating
D.Bottom estimating

2(2)处选择()

A.Perform Quality Assurance
B.Validate Scope
C.Control Quality
D.Define Scope

3(1)处选择()

A.PerformQualityAssurance
B.ValidateScope
C.ControlQuality
D.DefineScope